DPWH ramps up construction of Tacloban’s ‘grand canal’ project

By Sarwell Meniano | Philippine News Agency | November 17, 2026 1:08pm

NEW LINK. A portion of the PHP4.4 billion Tacloban-Palo Diversion Road in this Sept. 1, 2026 photo. The Department of Public Works and Highways (DPWH) is ramping up construction of the project despite the absence of an allocation for the project in the agency’s 2026 budget. (Photo courtesy of DPWH-8)

TACLOBAN CITY – The Department of Public Works and Highways in Eastern Visayas (DPWH-8) is ramping up construction of the PHP4.4 billion Tacloban-Palo Diversion Road despite the project not being allocated with new funding in the agency’s 2026 budget.

In a Tuesday update, the DPWH-8 said 756 meters of the road and drainage component have been completed, while 1.25 kilometers (km) are now under construction as of the end of October 2026.

 

PhilEnergy 2027 – Comprehensive Energy Trade Event in the Philippines

 

Ongoing activities fall under the DPWH’s 2024 and 2025 regular budget. Completed sections were funded by the 2019, 2023 and 2024 appropriations.

“While funding approval is not within our control, we hope that future funding will be approved and included in the national budget. The completion of this project will have a significant impact on our communities,” DPWH Eastern Visayas Regional Director Edgar Tabacon said in a statement.

At least PHP2.33 billion has been released as of 2025, and the remaining PHP2.1 billion has been proposed for funding in 2027 to complete the 3.23-km stretch of road and canal, according to DPWH-8.

 

Water Philippines 2027 – Philippines’ Leading International Water and Wastewater Event

 

Also known as the “Grand Canal,” the project is a four-lane highway spanning about 3.2 km from the San Jose district in Tacloban City to Campetic village in Palo, Leyte.

The project also includes a 16- to 22-meter-wide flood control and drainage system to be installed along the center of the road to reduce encroachment and prevent waterway clogging.

The larger drainage system is expected to mitigate flooding in the villages of Candahug, Pawing and Campetic in Palo, as well as in Caibaan, San Jose, Marasbaras and Manlurip, including V&G Subdivision and Imelda Village in Tacloban.

These areas typically experience prolonged flooding during heavy rains and typhoons, and floodwaters can take weeks to recede.

The diversion road, which will also include bike lanes, sidewalks, service roads, solar streetlights and road safety devices, is expected to transform idle and flood-prone lands into viable commercial areas.

Source: Philippine News Agency

.