Over a decade since Yolanda, thousands of housing units remain empty

By: Kurt Dela Peña | November 09, 2026

Composite image from INQUIRER FILE/JUNJIE MENDOZA/CEBU DAILY NEWS

MANILA, Philippines — Thousands of homes built for survivors of Super Typhoon Yolanda (Haiyan) remain unoccupied more than a decade after the storm devastated the Visayas, unleashing storm surges reaching about two meters high.

Through the National Housing Authority’s (NHA) Yolanda Permanent Housing Program, the government had a revised target of 194,195 units.

As of December 2025, only 176,804, or 91.04 percent, have been completed so far.

Out of this, 47,139 units remain vacant, according to the Commission on Audit’s (COA) 2025 Consolidated Report on the Audit of Disaster Risk Reduction and Management Funds released in August 2026.

In an analysis of the COA report, Inquirer data scientist Dr. Alicor Panao identified several reasons for the delays, including funding shortages, suspended projects, canceled contracts, land disputes, design changes, bad weather, and unsuitable sites.

Even completed houses remained unoccupied because land titles and subdivision plans were pending, utilities were unavailable, or construction defects needed repairs, said Panao, an associate professor at the University of the Philippines.

Yolanda, considered the strongest typhoon to hit the Philippines, affected 14 million people across 44 provinces, killing 6,340 and leaving 1,800 missing. The government estimated the damage at P95.4 billion.

Panao also noted that transferring completed housing units to local governments was often delayed, taking anywhere from 205 to 3,644 days, or nearly 10 years.

Poor transportation, limited livelihood opportunities, inadequate utilities, and substandard construction have discouraged beneficiaries from occupying the houses, he said. Over time, vacant units risk deterioration, vandalism, or unauthorized occupation.

The prolonged delays also risk wasting public funds and undermine policies requiring government resources to be protected from loss and waste, Panao said.

He added that many intended beneficiaries may have relocated, found alternative housing or no longer qualified by the time the units became available.

The COA warned that the delays could damage the NHA’s reputation for disaster response and erode public confidence in the agency’s ability to provide timely and adequate shelter to disaster survivors./dp